Regional road and bridge updates

FM 720 North – In May, the contractor will construct concrete sidewalks, lay asphalt, install concrete driveways and install seed/sod for northbound FM 720 lanes.

FM 455 – From west of FM 2450 to east of Marion Road, 30 percent plans are expected in early May. Illumination throughout the corridor is under discussion.

Mayhill Road – From north of Quail Creek Road to U.S. 380, old poles have been removed. Additional utility relocated needed at the U.S. 380 intersection are underway.

I-35E/Loop 288/Brinker/Mayhill – A new southbound exit ramp opened on April 9. Crews are constructing retaining walls and an entrance ramp as well as handling Brinker bridge drill shafts, Loop 288 drill shafts and the southbound main lane embankment.

Union Hill/ FM 455/ FM 2164 Realignment Project – For May, the focus will be on vegetation.

U.S. 380 East – (Loop 288 to U.S. 377) The TxDOT design team is working on 95 percent plans with an estimated timeline for submittal of May 2019. (U.S. 377 to county line) The consultant continues to work on the 95 percent plans. The estimated timeline for submittal is July 2019.

U.S. 380 Feasibility Study – Following public meetings in January, a second public meeting will be scheduled this summer.